Join
Search

Fission Stories #136: Scoring 100 on the Test by Changing the Questions

Bookmark and Share

For the first time in a long while, nuclear power plants are being built in the United States (Watts Bar Unit 2 really doesn’t count because it was “under construction” when I was in college back in the disco daze of the late 1970s). It would be solid and groovy if as many problems as possible experienced during construction back then are avoided now, like the problem experienced at the Zion nuclear plant in Illinois.

More than a year after the Atomic Energy Commission (NRC’s predecessor) issued operating licenses for the two reactors at Zion, workers discovered that sensors installed to detect low pressure in the steam pipes were wired according to the blueprints, but that the blueprints were wrong. These sensors had been put in place, tested, and accepted to be properly installed years earlier. Other workers launched an investigation into how this mistake was made and overlooked for so long.

The sensors were located in the pipes carrying steam from the steam generators to the turbine. If a pipe breaks, the pressure in that pipe drops. The sensors monitor pressure and initiate automatic plant responses, like shutting down the turbine and reactor, when appropriate. The mis-wired sensors meant that the plant would not respond to events as assumed in the safety studies.

During construction, workers noticed that the wiring in the plant did not match the blueprints. They communicated this situation back to Westinghouse, the reactor vendor. Westinghouse misunderstood the information they received. They thought that the sensors had been tested and that wiring changes had been made to correct deficiencies identified during the testing – a plausible scenario because functional testing often yields such outcomes. But no such testing had been conducted of these sensors. They had merely not been installed as specified on the blueprints.

Based on its mistaken perception, Westinghouse revised the blueprints to match how the sensors had been wired at the plant. In other words, Westinghouse “corrected” the blueprints to match the errors at the plant. When Westinghouse issued the revised blueprints, Sargent & Lundy (the architect/engineer for Zion) accepted the blueprints without any verification and included them among their “as-built” drawings for the plant. While the blueprints truly reflected the plant as it was built, it had been built wrongly.

Our Takeaway

The NRC’s regulations, particularly the quality assurance criteria in 10 CFR 50 Appendix B require plant owners to have effective programs to find and fix safety problems. Here, they scored 50% for having found safety problems but failing to fix them.

This event involved an error trap. Westinghouse received lots of reports from Zion about changes made to wiring arrangements as the result of functional testing results. As happened in this case, it was easy to mistake another report about blueprints not matching wiring configurations in the field as a request for another blueprint revision instead of a request to re-wire the sensors.

Over the past decade, the nuclear industry has emphasized three-way communications among operators. For example, a supervisor will instruct an operator to “start the alpha pump.” The operator will confirm understanding of the direction by responding something like “understood I am to start the alpha pump” and the supervisor will confirm correct understanding with something like “correct, you are to start the alpha pump.” The two verification steps avoid errors due to miscommunication.

Three-way communications can also avoid problems like those experienced by Westinghouse at Zion. Workers at Zion could have sent a message to Westinghouse about the difference between the actual wiring configuration and the blueprints. Westinghouse could have responded with its understanding of the difference as well as its expected resolution. Workers at Zion could have responded with confirmation that the situation and its solution were properly understood.

It’s literally as easy as 1-2-3.

 

“Fission Stories” is a weekly feature by Dave Lochbaum. For more information on nuclear power safety, see the nuclear safety section of UCS’s website and our interactive map, the Nuclear Power Information Tracker.

Posted in: fission stories Tags: , , ,

About the author: Mr. Lochbaum received a BS in Nuclear Engineering from the University of Tennessee in 1979 and worked as a nuclear engineer in nuclear power plants for 17 years. In 1992, he and a colleague identified a safety problem in a plant where they were working. When their concerns were ignored by the plant manager, the utility, and the Nuclear Regulatory Commission (NRC), they took the issue to Congress. The problem was eventually corrected at the original plant and at plants across the country. Lochbaum joined UCS in 1996 to work on nuclear power safety. He spent a year in 2009-10 working at the NRC Training Center in Tennessee. Areas of expertise: Nuclear power safety, nuclear technology and plant design, regulatory oversight, plant license renewal and decommissioning

Support from UCS members make work like this possible. Will you join us? Help UCS advance independent science for a healthy environment and a safer world.

Comments are closed. Comments are automatically closed after two weeks.

2 Responses

  1. Sean McKinnon says:

    David,

    What other methods were in place to detect steam line breaks at the time to back up these sensors?

  2. Richard says:

    It is more than a little worrisome that people/companies do not take the time to verify what they are doing. That extra third step can make a huge difference when it comes to SAFETY! Are they in such a hurry to make a profit that they don’t bother?!?